01Where phases are set

Manage → Phasing → Phases. The first tab, Project Phases, lists the phases in time order: by default Existing and New Construction. Add more with Insert Before or Insert After, for a project built in stages. The other two tabs hold the Phase Filters and the Graphic Overrides.

Do not add a “Demolition” phase. Demolition is not a period of its own in Revit: an element is demolished in a phase, normally New Construction. A separate demolition phase only doubles the number of views you have to keep right.

02Phase Created and Phase Demolished

Select any wall, door or floor and look at the bottom of Properties. Phase Created is the phase in which it appears; Phase Demolished is the phase in which it goes, or None. When you draw an element, Phase Created is the phase of the active view. To demolish, use Modify → Geometry → Demolish (the hammer) and click the elements: Revit sets their Phase Demolished to the phase of the view.

03Phase filters: what each view shows

Every view has two settings in Properties: Phase and Phase Filter. Seen from the view’s phase, each element is one of four things:

  • Existing: created in an earlier phase and still standing.
  • Demolished: created earlier and demolished in this phase.
  • New: created in this phase.
  • Temporary: created and demolished in this phase, such as site hoarding.

The phase filter decides, for each of the four, whether it is shown by category, shown with the graphic override, or not shown. For a refurbishment, set up three plans of the same level:

PlanPhasePhase filter
ExistingExistingShow Complete
DemolitionNew ConstructionShow Previous + Demo
ProposedNew ConstructionShow Previous + New

Put the phase and the phase filter into each view template, so a new plan made from the template is right from the start.

04Graphic overrides

The Graphic Overrides tab sets how existing, demolished, new and temporary elements look when a filter says “Overridden”: line pattern, line weight, colour, halftone, cut and surface patterns. A common set is existing in grey or halftone, demolished dashed, and new by category, so new work is the darkest thing on the sheet. Check what your local standard or client asks for: some want demolition in yellow and new work in red.

05Doors and windows in demolished walls

  • Demolish a wall, and the doors and windows hosted in it are demolished with it.
  • Demolish an existing door or window, and Revit fills the opening with an infill wall in that phase, so the proposed plan shows a closed wall.
  • A new door in an existing wall: draw it in a view set to New Construction. The opening appears only from that phase on; the existing plan still shows the wall whole.

06Rooms, schedules and linked models

Rooms belong to a phase. A room placed in the existing plan does not exist in the proposed plan: place the rooms again in a New Construction view, with the new names and areas. Schedules have their own Phase and Phase Filter, so an area schedule can list the existing or the proposed rooms. For linked models, map their phases to yours in the link’s Type Properties → Phase Mapping.

07Why a wall disappears

  • It was drawn in the wrong view. A wall drawn in the existing plan is Existing; one drawn in a proposed plan is New and is not shown in the existing plan. Fix it in Properties → Phase Created.
  • The filter hides it. Show New hides everything existing. Switch the view to Show Previous + New, or Show All, to find it.
  • It was demolished. Check Phase Demolished: a demolished element disappears from later phases.
  • Everything looks grey. The elements are Existing because they were drawn in an earlier phase than the view. Select them and change Phase Created.

Rule of thumb: before drawing anything in a refurbishment, look at the view’s Phase in Properties. Two seconds there save an hour of changing Phase Created on hundreds of elements.

08Phase filter greyed out, and phases in links

If Phase or Phase Filter is greyed out in a view’s Properties, its view template controls them. Change them in the template, or untick their Include so each view sets its own; more in Revit view templates. For a linked model, Revit maps each of its phases to one of yours: select the link, Edit Type → Phase Mapping, and pick the host phase for each. Keep the link By Host View in Visibility/Graphics so it follows the view’s phase filter.

Phases set before the first line

The DATUM Revit template comes with its phases, phase filters and graphic overrides already set, so the existing, demolition and proposed plans of a refurbishment read the same on every project.

A sheet from the DATUM Revit templateDATUM for RevitThe Revit architecture templatePhases, view templates, title blocks, tags and schedules on one standard.See the template →

Questions

How do phases work in Revit?

Every element has a Phase Created and a Phase Demolished, and every view shows one phase through a phase filter. Seen from the view’s phase, each element is existing, demolished, new or temporary, and the filter decides whether each of these is shown, shown with an override, or hidden.

How do I show demolition in Revit?

Use Modify → Geometry → Demolish in a view set to New Construction, then make a demolition plan with Phase New Construction and the phase filter Show Previous + Demo. Demolished elements then appear with the demolished graphic override, usually dashed.

Why did my wall disappear in Revit?

Most often it was drawn in a view of another phase, so the current phase filter hides it. Set the view to Show All to find it, then correct its Phase Created or Phase Demolished in Properties.